The duration of a landed project is primarily dictated by its structural complexity. On average, timelines are categorized as follows:
- Interior Refurbishment: 9 – 13 Months
- Additions & Alterations (A&A): 11 – 14 Months
- Full Reconstruction: 18 – 24 Months
Navigating Potential Delays:
Landed projects in Singapore require meticulous coordination with authorities including URA, BCA, PUB, and SCDF. A delay in a single clearance can impact the entire schedule. At SG Livinghub, we mitigate this through proactive permit management and early procurement of long-lead items—such as imported marble or bespoke fixtures—to ensure global supply chain fluctuations do not stall your home’s progress.